I recently had a conversation with a product owner that wanted to have the Scrum team broken up into smaller units so that less time was wasted on the Scrum Ceremonies! Their complaint was around the need in Scrum to have the entire “Team” (7+-2) involved in the sizing of the work during the “Sprint Planning Meeting”.
Update 16th March 2010
- Kane Mar , the man who taught me Scrum, made a fantastic comment after reading this and I have added it in.
The standard flippant answer of all Scrum professionals, “Well that’s not Scrum”, does not get you any brownie points in these situations. The response could be “Well we are not doing Scrum then” which in turn leads to “We are doing Scrum…But, we have split the scrum team into units of 2/3 so that they can concentrate on a specific area of work”. While this may work, it is not Scrum and should not be called so… It is just a form of Agile. Don’t get me wrong at this stage, there is nothing wrong with Agile, just don’t call it Scrum.
The reason that the Product Owner wants to do this is that, in effect, through a number of miscommunications and failings in our implementation of Scrum, there was NO unit of potentially Shippable software at the end of the first sprint. It does not matter to them that most Scrum teams will fail the first Sprint, even those that are high performing teams. Remember it is the product owners their money!
We should NOT break up scrum teams into smaller units for the purpose of having less people tied up in the Scrum Ceremonies.
The amount of backlog the Team selects is solely up to the Team… Only the Team can assess what it can accomplish over the upcoming Sprint.
- Scrum Guide , Scrum.org
The entire team must accept the work and in order to understand what they can accept they must be free to size it as a team. This both encourages common understanding and increases visibility on why team members think a task is of a particular size. This has the benefit of increasing the knowledge of the entire team in the problem domain.
A new Team often first realizes that it will either sink or swim as a Team, not individually, in this meeting. The Team realizes that it must rely on itself. As it realizes this, it starts to self-organize to take on the characteristics and behaviour of a real Team.
- Scrum Guide , Scrum.org
This paragraph goes to the why of having the whole team at the meeting; The goal of Scrum it to produce a unit of potentially shippable software at the end of every Sprint. In order to achieve this we need high performing teams and this is what Scrum as a framework has been optimised to produce.
I think that our Product Owner is understandably upset over loosing two weeks work and is losing sight the end goal of Scrum in the failures of the moment. As the man spending the money, I completely understand his perspective and I think that we should not have started Scrum on an internal project, but selected a customer that is open to the ideas and complications of Scrum.
So, what should we have NOT done on our first Scrum project:
- Should not have had 3 interns as the only on site resource – This lead to bad practices as the experienced guys were not there helping and correcting as they usually would.
- Should not have had the only experienced guys offsite – With both the experienced technical guys in completely different time zones it was difficult to get time for questions. Helping the guys on site was just plain impossible.
- Should not have used a part time ScrumMaster – Although the ScrumMaster attended all of the Ceremonies, because they are only in 2 full days of the week it makes it difficult for the team to raise impediments as they go.
- Should not have used a proxy product owner. – This was probably the worst decision that was made. Mainly because the proxy product owner did not have the same vision as the product owner. While Scrum does not explicitly reject the idea of a Proxy Product Owner, I do not think it works very well in practice. The “single wringable neck” needs to contain both the Money and the Vision as well as attending the required meetings.
“Your team may be dysfunctional … but at least you can see the impediments. Now you have the ability to do something about it!”
- Kane Mar – Scrumology , Scrum Coach
I will be brining all of these things up at the Sprint Retrospective and we will learn from our mistakes and move on.
Do, Inspect then Adapt…
Need Help?
Professional Scrum Developer Training
SSW has six Professional Scrum Developer Trainers who specialise in training your developers in implementing Scrum with Microsoft’s Visual Studio ALM tools.
Smart Classifications
Each classification [Concepts, Categories, & Tags] was assigned using AI-powered semantic analysis and scored across relevance, depth, and alignment. Final decisions? Still human. Always traceable. Hover to see how it applies.
What to read next
My first Scrum team in the wild
A real-world account of guiding a new Scrum team through their first sprint, covering estimation, story points, sprint planning, and …
Adventures in Scrum: Lesson 2 - For the record
Highlights the importance of clear communication and documenting disagreements in Scrum to prevent misunderstandings and failed sprints, …
Scrum is hard to adopt and disruptive to your organisation
Explains why adopting Scrum is challenging and disruptive, highlighting the need for training, mentoring, and dedication for successful …
The Insufficiency of Scrum is a fallacy
Scrum alone does not cause project failure; lacking strong engineering practices and effective retrospectives leads to technical debt and …
Product Owners are not a myth
Explains the Product Owner role in Scrum, common challenges with proxies, and how support teams like Business Analysts can help manage large …
What does a poor scrum team look, act and feel like?
Explores signs of a poor scrum team, including autocratic leadership, dysfunctional product ownership, lack of trust, and organisational …
Detecting agile theatre with real delivery signals
Why Most Companies Operating Models Fail in Dynamic Markets
A concise comparison of Predictive and Adaptive Operating Models, explaining why traditional structures fail in dynamic markets and how …
Don’t Manage Dependencies, Remove Them
Explains why dependencies are a sign of poor system design and outlines steps to eliminate them by aligning teams, clarifying ownership, and …
The Estimation Trap: How Tracking Accuracy Undermines Trust, Flow, and Value in Software Delivery
Tracking estimation accuracy in software delivery leads to mistrust, fear, and distorted behaviours. Focus on customer value, flow, and …
Flow of Value vs Flow of Work – Misnomer or Useful Shorthand?
Compares “flow of value” and “flow of work” in Kanban, explaining why only validated outcomes count as value and stressing the need for …
Why Outsourcing DevOps Fails, and How Real Engineering Excellence Starts With Your Team
Avoid DevOps vendor lock-in, discover how true engineering excellence starts with partnership, not outsourcing. Ready to transform your …
The Definition of Done is a Commitment to Quality
Defines the Definition of Done in Scrum as a clear, shared standard for quality, ensuring increments are releasable, transparent, and …
Why Your Definition of “Done” Is Holding Back Quality, Agility, and Trust, And How to Raise the Bar
Is your team’s “done” really done? Discover how a clear, objective definition of done boosts quality, agility, and trust in product …
Acceptance Criteria vs Definition of Done: Why Getting This Right Builds Trust and Delivers Quality Faster
Stop confusing acceptance criteria with definition of done, learn the crucial difference to boost quality, speed, and trust in your agile …
How to Evolve Your Definition of Done: Start Small, Grow Smarter, and Build Lasting Momentum
Unlock a smarter Definition of Done, start small, evolve standards, and build team momentum without overwhelm. Discover how progress drives …
Why Most Transformations Fail Without Honest Conversations
Most transformations fail without open, honest conversations that address real issues, making transparency and tough dialogue essential for …
Why Your Definition of Done Is the Secret Weapon for Real Business Impact and Agile Growth
Transform your definition of done into a strategic advantage, deliver real value, reduce risk, and drive business impact with every sprint.