As part of the Scrum.org webinar “Ask a Professional Scrum Trainer - Martin Hinshelwood - Answering Your Most Pressing Scrum Questions” I was asked a number of questions. Since not only was I on the spot and live, I thought that I should answer each question that was asked again here, as well as those questions I did not get to.
In case you missed it, here is the recording of yesterday’s Ask a Professional Scrum Trainer webinar with Martin Hinshelwood! Watch here: http://ow.ly/ijiM50vwEkD
[Question] In Nexus with 5 Scrum teams, how can the Product Owner attend all Sprint Planning events?
As you increase the number of Teams in a Nexus you can very quickly run into this common scaling issue. While Nexus talks about a single Product Owner who has overall accountability and ownership of the Product Backlog, you may need to scale the Product Owner role as your Nexus grows. My usual starting point here is to look at how the Product Backlog is decomposed. It may be that my Product Owner only provides detailed leadership down to the Feature level and not to the Product Backlog Level. This leaves the Scrum Team with ownership there, and releases pressure on the Product Owner. The Product Owner would then only require to attend the Nexus Sprint Planning portion, and would delegate the rest. As long as the Product Owner effectively communicates their vision & expectations as part of the Nexus Sprint Goals, the Scrum Teams should be able to work towards fulfilling them.
Product Backlog Items can be delivered in a singe Sprint with a preference for smaller.
Features are too big for a single team Sprint and may be delivered across multiple Sprints or Teams
Epics are too big for a Release and would be composed of many Features.
-Martin Hinshelwood
Each Scrum Team would then be free to choose how they manage this and make sure that they have enough ready Backlog Items for their part of Sprint Planning. Usually they will designate, or have, a virtual Product Owner that is dedicated to their team. This virtual PO role could be called a “Area Owner” if their Scrum Team is focused on only one area of the Product, or a “Team Owner” if there are many teams in the same area. This is roughly how the Azure DevOps engineering teams break down:
-Product Owner
|—-Work Item Product Owner
|— Team A Product Owner
|—Team B Product Owner
|—-Source Control Product Owner
|—-etc.
In this case they have ~42 teams that roll up to ~6 Product Areas, and is just one example of how you might structure things. The danger is in disrupting the flow of information by increasing the distance between the Product Owner and the Development Team. The Azure DevOps engineering teams mitigate this with Autonomy. Each Area Owner is only looking at their functional area while fulfilling the vision set by the Product Owner, and the Team Owner is communicating constantly with their peers and the Area Owner.
If you do implement some kind of hierarchy I recommend focusing on keeping it as flat as posible and understanding that each of these folks, Product Owner, Area Owner, & Team Owner are fulfilling the role of the Product Owner as per the Scrum Guide as part of a Scrum Team. For the question above I would likely start with a dedicated Team Owner for each team that is the representative that attends the Nexus Sprint Planning and that works closely with the Product Owner. This will likely need close monitoring and a skilled Scrum Master to help coach the teams to maintain communication and not loose focus.
While there are no right answers there are some answers that are better than others. For your given situation select the most right answer, and iteration to the best version of it.
Smart Classifications
Each classification [Concepts, Categories, & Tags] was assigned using AI-powered semantic analysis and scored across relevance, depth, and alignment. Final decisions? Still human. Always traceable. Hover to see how it applies.
What to read next
What's the best way to work around multiple PO?
Guidance on addressing issues with multiple Product Owners in Scrum, highlighting the need for clear backlog ownership and accountability to …
How do you incorporate a Design Sprint in Scrum?
Explains how to integrate Design Sprint activities within Scrum by embedding design and UX work into regular sprints and backlog refinement, …
No Estimates and is it advisable for a Scrum Team to adopt it?
Explores whether Scrum Teams should adopt No Estimates, comparing estimation methods, team maturity, and metrics like cycle time, …
How do you handle conflict in a Scrum Team?
Guidance on resolving conflict in Scrum Teams, including facilitation techniques, escalation steps, and the Scrum Master's role in fostering …
What is your perspective on collocation?
Explores the benefits and challenges of collocation in Scrum teams, comparing face-to-face collaboration with remote work, and offering …
Detecting agile theatre with real delivery signals
Why Most Companies Operating Models Fail in Dynamic Markets
A concise comparison of Predictive and Adaptive Operating Models, explaining why traditional structures fail in dynamic markets and how …
Don’t Manage Dependencies, Remove Them
Explains why dependencies are a sign of poor system design and outlines steps to eliminate them by aligning teams, clarifying ownership, and …
The Estimation Trap: How Tracking Accuracy Undermines Trust, Flow, and Value in Software Delivery
Tracking estimation accuracy in software delivery leads to mistrust, fear, and distorted behaviours. Focus on customer value, flow, and …
Flow of Value vs Flow of Work – Misnomer or Useful Shorthand?
Compares “flow of value” and “flow of work” in Kanban, explaining why only validated outcomes count as value and stressing the need for …
Why Outsourcing DevOps Fails, and How Real Engineering Excellence Starts With Your Team
Avoid DevOps vendor lock-in, discover how true engineering excellence starts with partnership, not outsourcing. Ready to transform your …
The Definition of Done is a Commitment to Quality
Defines the Definition of Done in Scrum as a clear, shared standard for quality, ensuring increments are releasable, transparent, and …
Why Your Definition of “Done” Is Holding Back Quality, Agility, and Trust, And How to Raise the Bar
Is your team’s “done” really done? Discover how a clear, objective definition of done boosts quality, agility, and trust in product …
Acceptance Criteria vs Definition of Done: Why Getting This Right Builds Trust and Delivers Quality Faster
Stop confusing acceptance criteria with definition of done, learn the crucial difference to boost quality, speed, and trust in your agile …
How to Evolve Your Definition of Done: Start Small, Grow Smarter, and Build Lasting Momentum
Unlock a smarter Definition of Done, start small, evolve standards, and build team momentum without overwhelm. Discover how progress drives …
Why Most Transformations Fail Without Honest Conversations
Most transformations fail without open, honest conversations that address real issues, making transparency and tough dialogue essential for …
Why Your Definition of Done Is the Secret Weapon for Real Business Impact and Agile Growth
Transform your definition of done into a strategic advantage, deliver real value, reduce risk, and drive business impact with every sprint.
Why Most Companies Operating Models Fail in Dynamic Markets
A concise comparison of Predictive and Adaptive Operating Models, explaining why traditional structures fail in dynamic markets and how …
Don’t Manage Dependencies, Remove Them
Explains why dependencies are a sign of poor system design and outlines steps to eliminate them by aligning teams, clarifying ownership, and …
The Estimation Trap: How Tracking Accuracy Undermines Trust, Flow, and Value in Software Delivery
Tracking estimation accuracy in software delivery leads to mistrust, fear, and distorted behaviours. Focus on customer value, flow, and …
Kendall Guide - A System of Work for AI Adoption
Flow of Value vs Flow of Work – Misnomer or Useful Shorthand?
Compares “flow of value” and “flow of work” in Kanban, explaining why only validated outcomes count as value and stressing the need for …
Estimating Better in an Overloaded System Is a Poor Man’s Strategy
High work in progress (WIP) causes delays and unpredictability; improving estimates won’t help. Limiting WIP and focusing on flow is key to …